Project Plan

Plan updated 7/12/23

February, 2023Publish survey to collect information from Norristown Community
February  28, 2023First Community meeting to kick off project, present plan
May, 2023Publish Requests For Proposals for:  
  • Community stakeholder management consultant                                                                                             
  • Asset inventory study + design (architect / planning / engineering firm
February - June2023Collect survey data; publish results
June-July, 2023Secure asset inventory + stakeholder study consultant; commence study
May - August, 2023Once monthly status update community meeting (virtual / in-person)  
  • Identify stakeholder committee 
September, 2023Physical Asset and community service reports complete
June - October, 2023Design programming meetings (w/ stakeholders) and documentation (concept phase)
September - November, 2023Schematic Design phase 
  • Includes design proposals taking into asset inventory, program of requirements, stakeholder presentations 
  • Deliver sustainable operations plan (meaning: who will run facility/-ies after completion?)
November - December, 2023Design plan adoption through stakeholder meetings and confirm feasibility of operations plan. 
  • Identify plan to transition from County Recovery Office project management to facility operator, including timeframe
January  – March, 2024Design Development for facility/-ies construction / renovations 
  • Architect will produce plans for consideration / approval by Community stakeholder committee
March - September, 2024 Construction Documents 
  • Architect will produce plans for consideration / approval by Community stakeholder committee
October 2024 – February, 2025Procurement for construction contractors 
February, 2025 – June, 2026 Construction completed