Montgomery County’s Ridge Pike Improvement Project is a complex and lengthy roadway, drainage, sidewalk, and lighting construction project. This web page will list current construction updates that will affect traffic flows along the corridor, and will be frequently updated as the County’s construction contractors complete various activities.
March 18, 2023
Please be advised that Allan Myers is planning to work Saturdays during Stage 1 (thru approximately mid-May), this includes tomorrow (3/18). Saturday work is being done to assist with making up lost days due to weather, and delayed utility relocations in an effort to advance the schedule. They will be working along Ridge Pike between Crescent Avenue and Northwestern Avenue from 7am – 3pm most Saturdays.
March 17, 2023
The roadway contractor will be working Saturdays between Crescent Avenue and Northwestern Avenue beginning on 3/18/2023 between the hours of 7am – 3pm. Please be prepared for possible lane restrictions.
March 18, 2023 – May 2023
Work will occur on Saturdays starting March 18, 2023 through around mid-May 2023 along Ridge Pike between Crescent Avenue and Northwestern Avenue from 7 a.m. – 3 p.m. Saturday work is being done to make up for lost days, due to weather and delayed utility relocations, in an effort to advance the schedule.
March 8, 2023 – May 2023
Single-lane road closures will be in effect on Ridge Pike from Pine Ridge Road through Northwestern Avenue in the eastbound direction and from Northwestern Avenue to Park Avenue in the westbound direction. In addition, left turns on Manor Road will not be permitted. Lane closures will occur between the hours of 6:30 a.m. and 3:30 p.m. Monday through Friday. No evening or weekend closures are expected at this time. This lane closure will be a permanent configuration in effect through May 2023.
September 6, 2022
Barren Hill Road will have intermittent single lane closures on Tuesday, September 6, 2022. Single lane closures with flagging will be in effect from 9 a.m. to 3 p.m. on Barren Hill Road between Ridge Pike and Harts Lane for soil testing. The public is urged to use caution while traveling in construction zones.
August 22 – August 26, 2022
Pre-construction activities will continue on Ridge Pike between Crescent Avenue and Northwestern Avenue during the week of Monday, August 22, 2022. Single lane closures with flagging will be in effect from 9 a.m. to 3 p.m. from August 22-26 in various locations throughout the corridor for tree clearing and utility relocation. The public is urged to use caution while traveling in construction zones.
August 15 – August 19, 2022
Pre-construction activities will continue on Ridge Pike between Crescent Avenue and Northwestern Avenue during the week of Monday, August 15, 2022. Single lane closures with flagging will be in effect from 9 a.m. to 3 p.m. from August 15-19 in various locations throughout the corridor for tree clearing and utility relocation. The public is urged to use caution while traveling in construction zones.
August 8 – August 17, 2022
Rolling lane closures will occur along Ridge Pike from Crescent Avenue to Philadelphia in preparation for construction work. A temporary signal has been installed at the intersection of Manor Road and Ridge Pike and will go live on 8/10/2022. Residents and commuters may notice a slight difference in the timing of the new signal. The next intersection to receive a temporary signal will be Church Road/Harts Lane and Ridge Pike.
August 1 – August 7, 2022
Pre-construction activities will continue on Ridge Pike between Crescent Avenue and Northwestern Avenue during the week of Monday, August 1, 2022. Single lane closures with flagging will be in effect from 9 a.m. to 3 p.m. from August 1-5 in various locations throughout the corridor for tree clearing and utility relocation. The public is urged to use caution while traveling in construction zones.
July 25 – July 30, 2022
Pre-construction activities will continue on Ridge Pike between Crescent Avenue and Northwestern Avenue the week of Monday, July 25, 2022. Single lane closures with flagging will be in effect from 9 AM to 3 PM during the week of the 25th in various locations throughout the corridor for tree clearing and utility relocation. Please use caution while traveling in construction zones.
July 18 – July 22, 2022
Pre-construction activities will begin on Ridge Pike between Crescent Avenue and Northwestern Avenue on Monday, July 18, 2022. Single lane closures with flagging will be in effect from 9 AM to 3 PM during the week of the 18th in various locations throughout the corridor for tree clearing. Please use caution while traveling in construction zones.