The Justice Center Project ties three complex projects into one, constructing a new, modern County justice center, completely renovating the existing historic courthouse facility, and more than doubling the size of the reimagined Hancock Square park as accessible, and active public green space right in the downtown. Phased over 5 years, the project will provide:

Justice Center Infographic 2

New Justice Center
A 325,000-square-foot, six story new building connected to the existing courthouse housing new courtrooms, court-related offices, and public spaces.

Hancock Square Park
Reconstructed Hancock Square park, expanded from the current 23,000 square feet to 57,000 square feet, incorporating carefully planned native landscape plantings, direct access from Main Street, and respectful incorporation of current monuments into reflective spaces.

Historic Courthouse
Complete renovation of the existing courthouse, incorporating detailed attention to historic preservation and a full replacement of all utility infrastructure systems.

Project Plan

  • PHASE 1 – Demolition of parking garage, Wells Fargo bank building, and work to prepare Hancock Square Park for renovation. This began in March 2021 and was completed December 2021.
  • PHASE 2 – Construction of Justice Center south building. Construction began December 2021 and is expected to be completed by late 2024.
  • PHASE 3 – Renovation of historic courthouse. Scheduled to begin Spring 2024 and be completed by end of 2026.